Not everybody took the long weekend off. Some KADYN employees worked the Glenbrook Rail Possession. Another successful drainage job completed with our partner John Holland Rail.

Removing a section of platform and 2 sets of tracks, we then excavated 3 metres deep and installed a new drainage culvert. In the 3 day possession the drainage was installed and the track re-instated along with the platform slab. We will return to Glenbrook in January and re-instate the heritage listed brickwalls supporting the platform slab.